Please note that construction schedules are subject to change due to weather, site issues, etc.

Reference this Construction MAP to view the impacted construction areas for next week.

Unsure about which is your area? Visit the Blueprint map and type in your address to find out!

Please remember, Blueprint Columbus is funded by the City of Columbus’ Department of Public Utilities. There is no direct cost for any of our services to the residents. We have received reports there are private contractors in the area soliciting for similar work. If you are solicited about any work related to sump pumps, lateral lining, or downspout redirection, contact our Outreach Team to confirm you are in a Blueprint Neighborhood and will be receiving FREE services.

New Updates

Sump pump installations are offered for a limited time only! We have a few spots left on our list! If you are interested, contact us ASAP and we’ll schedule your no-obligation assessment to see if a sump pump is right for you!

Overbrook Chatham

  • Private property investigations for downspout redirection and lateral lining for this area are in progress.
    • A crew will be in conducting lateral linings on Chatham Rd.
  • Ohio Basement Authority has completed all of their investigations. Residents should be receiving notices to schedule a homeowner meeting to discuss any proposed work for their property. Please be on the lookout for this notice.
    • There will be installations performed on Wynding, Glenmont, Overbrook and Chatham Rd.

Cooke Glenmont

  • Private property investigations for downspout redirection and lateral lining for this area are in progress.
    • Crews are scheduling homeowner meetings with residents at this time in preparation of the installations. Please take action and schedule these appointments if you have received notices to do so.
      • There will be installations being performed on Glenmont Ave. and Canyon Dr., Cooke Rd., and Glenmont PL.
    • Musson Brothers, the contractor conducting the lateral lining will be working on Canyon Dr., Glenmont Ave/PL, and Sharon installing liners on the lateral.

Morse Dominion

  • Shelly & Sands will not be onsite this week. Reseeding and some sign relocation/removal were performed this prior week.
  • Additional plantings are being ordered. We will provide more information about replantings once we receive this information.
  • BLD will conduct lateral linings in the easement between Wetmore/Beaumont, Beaumont/Garden, Weisheimer and E Dominion.
  • Ohio Basement Authority has completed all downspout work in the area.

Project Status

Weisheimer Indian Springs

  • Igel has completed all their downspout installations.
  • BLD will not be onsite this week.
  • Rain gardens will continue to have monthly cleanout/maintenance performed.

Blenheim Glencoe

  • Eramo will continue to conduct routine maintenance on the rain gardens.
  • Trees plantings will begin this November
  •  Additional evaluations are being conducted in conjunction with repaving plans. Schedules are being finalized with the repaving contractor.
  • Private property investigations for downspout redirection and lateral lining for this area will begin late 2019. Residents will receive a letter when this area is “activated”.
  • From Department of Public Service: Glencoe Rd. Resurfacing Update
    • Work begins 10/14 on Glencoe Rd. between High St. and Torrence Rd.
      • The asphalt pavement on Glencoe Rd. will be removed
      • The road base and subgrade on Glencoe Rd. will be stabilized with cement, graded and compacted.                                                                                                                                                                 
      •  This work is scheduled to be completed between the hours of 7 a.m. and 7 p.m.
    • Vehicle access will be restricted during cement application.                                                                 
      • Temporary Ramps will be placed at the driveway entrances along Glencoe Rd. following grading and compaction.
  • There will be very limited access to driveways during the construction activities.
  • Vehicles may be parked on connecting side streets during work hours.
    • No Parking signs will be posted the 3 days before.
    • For questions on this work, please contact 311 (645-3111)
  • From Department of Public Service: Blenheim Road resurfacing Update
    • The City of Columbus makes critical investments in street resurfacing projects like Blenheim to improve the quality of our roadways and infrastructure that residents depend on every day. Relocation of the main gas line on Blenheim by Columbia Gas must be completed before the city rebuilds and paves the street so the utility construction doesn’t tear up a newly resurfaced street. Delays in Columbia Gas completing the main gas line relocation have pushed the Blenheim resurfacing project to next spring. Columbia Gas will be working on the relocation this fall and winter.
    • For questions on this work, please contact 311 (645-3111)

Schreyer Springs

  • Facemyer has completed all project work within the project work zone. Rain gardens will continue to have a monthly cleanout/maintenance performed on them.
  • Downspout installations are complete.
  • Lateral Lining will begin in 2020.

General Notices

  • Several streets are slated for repaving in conjunction with Department of Public Service. Repaving schedules are currently being finalized with the contractor in most areas. When Blueprint receives schedule information from the Department of Public Service, we will also include that information in these notices.
  • The rain gardens are designed to drain in 48 hours or less. Some standing water within the garden after a rain event is normal. However, if the rain gardens are overflowing or have standing water for more than 2 days, please report that to blueprint@columbus.gov or 311.
  • Just like a normal storm drain, the rain gardens can’t do their job if leaves/debris are piling up and blocking water from entering the inlet. Our crews will clear these inlets during regular maintenance, but if you see leaves piling up and blocking the rain garden inlets, feel free to push them aside to allow rainwater to enter. And, as always, remember to keep leaves and yard waste out of the streets as much as possible.

Please contact 614-645-1253 or blueprint@columbus.gov with any questions you may have. If you have an emergency, please call 614-645-8276 for Water or 614-645-7102 for Sewers.